Ash Grove

Location
Industry
Construction
Labor
Project Duration
Outage Window
Technology
Ash Grove, A CRH Company Logo
Aerial view of a construction site where five workers in yellow safety vests work around a large rectangular foundation with gravel, dirt, pipes, a tarp, and two pieces of heavy machinery nearby.

Services Performed

Existing Conditions

Ash Grove operates a natural pozzolan facility in Tooele, Utah, where raw volcanic ash is dried, ground, and prepared for regional delivery. Because pozzolan reactivity improves as particle size decreases, reliable grinding, material handling, and controls are essential to meeting product performance requirements.

Ash Grove identified three primary objectives for the project: remove electrical and controls constraints that were limiting growth, connect a new product silo, and replace an unsupported OEM automation platform with a system that could be serviced locally and scaled over time. All of this work needed to be completed while protecting ongoing shipments and production.

The existing electrical room had no room for expansion and offered limited ability to isolate systems for maintenance. Field wiring reflected years of incremental changes, which slowed troubleshooting and increased operational risk. The automation platform in place had limited support in the United States, leaving the site without a dependable path to service when issues arose. The facility also operates under MSHA 48b regulations, requiring strict training and safety compliance.

Project Approach

KE began the project with a comprehensive plant-wide electrical audit, documenting cable identification, terminations, and system conditions. This audit established a clear baseline and directly informed the design of the new MCC room, electrical distribution strategy, and automation replacement.

The overall project spanned approximately seven months, with KE mobilizing in mid-November 2024 and completing construction in late June 2025. A new MCC room was designed and built approximately 200 feet from the original to improve capacity, provide clear isolation points, and allow for future expansion. New MCCs were procured, installed, and commissioned as part of a shift from a plant-wide electrical approach to a system-based design. Underground conduit and cable tray infrastructure were installed well in advance of the outage to support both the new silo and long-term plant growth.

A single, highly coordinated outage occurred roughly midway through the electrical construction. While much of the silo work continued outside the outage window, this outage focused on energizing MCCs, landing cables, migrating all I/O from the old PLC to the new PLC, implementing a new FactoryTalk-based automation program, and restarting an operating facility. The outage was originally scheduled for 14 calendar days, but KE had the plant moving product again within 10 to 11 days.

The success of the outage was driven by tight coordination with Ash Grove and other trades, accurate scheduling, and clear communication. Approximately seven automation engineers were on site throughout the outage, working alongside KE’s electrical crews. The outage represented the most automation-intensive phase of the project and would not have been successful without full on-site staffing and collaboration.

Cable tray installation was completed prior to the outage. During the outage itself, KE focused on relocating and reconnecting existing cables rather than installing new tray. Full device checkout, loop testing, and permissive testing were completed to ensure safe and predictable startup. All personnel completed MSHA 48b training, and daily hazard assessments addressed mobile equipment, confined spaces, high walls, and energized work. A dedicated QAQC lead verified installations and test results before turnover.

Following startup, KE’s automation team continued to provide remote support to quickly resolve any operational issues and ensure a smooth transition to steady-state operation.

The Impact

The project delivered a modernized electrical and automation system while returning the facility to operation ahead of schedule. Ash Grove now has a new MCC room with clear isolation points and space for growth, along with new MCCs, cable tray, and conduit infrastructure that supports current operations and future additions. Underground raceways and field wiring allowed the new product silo to be integrated efficiently.

The facility now operates on a modern, supportable PLC and FactoryTalk automation platform with documented I/O and consistent HMI standards. A complete checkout package, including loop sheets and as-built documentation, supports ongoing maintenance and troubleshooting. Electrical and automation work was executed under a single, coordinated plan, allowing parallel task execution and a controlled restart of production systems.

By strengthening the electrical infrastructure and modernizing controls, the Tooele facility is better positioned to meet growing demand for natural pozzolan in a region with limited fly-ash availability. Improved reliability and serviceability support lower-carbon concrete production while positioning the plant for future improvements.

Ash Grove now operates with a more maintainable, expandable facility and a locally supported automation platform that meets current production needs and supports long-term growth.

Building on this success, KE is continuing to collaborate with Ash Grove on additional projects that further support their operational goals and long-term growth.